processing plan工艺方案

-
Blind Plate Summary Table 盲板登记表 2019-10-17
-
No.1 Refinery Start-up Plan 炼油一部开工方案 2019-10-16
- Task Sheet for Crude Oil Entering Pre-dist. Column Process原油进装置至初馏塔流程任务单2019-08-30
- Task Sheet for Pre-dist. Bottom Oil to Atm. Tower Process初馏塔底油至常压塔流程任务单2019-08-30
- Task Sheet for Atm. Bottom Oil to Vac. Tower Process常压塔底油至减压塔流程任务单2019-08-30
- Task Sheet for Vacuum Residual Oil Process减压渣油流程任务单2019-08-30
- Caustic Recycling Process in Acid Gas & LPG Treating Unit产品精制装置碱液改循环流程2019-08-30
- Electric Desalting System is changed to Start-up Process电脱盐系统流程改开工流程2019-08-30
- Pre-dist. Tower System is changed to Start-up Process初馏塔系统改开工流程2019-08-30
- Atm. Tower System is changed to Start-up Process常压塔系统改开工流程2019-08-30
- Task Sheet for Blind Plate of B.L. Direction Adjustment界区盲板调向任务单 (1)2019-08-30
- Task Sheet for Vac. Middle Section Diesel Circulation Process Confirmation减压中段柴油循环流程确认任务单 2019-08-30
- Task Sheet for Amine ISBL/OSBL Blind Plate Adjustment胺液进出装置盲板调通任务单2019-08-30
- Task Sheet for Atm. Middle Section Diesel Circulation Process Confirmation常压中段柴油循环流程确认任务单2019-08-30
- Task Sheet for Overall Diesel Circulation Process Confirmation柴油循环大流程确认任务单2019-08-30
- Task Sheet for Crude Oil Process Confirmation原油流程再确认任务单2019-08-30